Take a fresh look at your lifestyle.

FG approves N87.5b contracts for roads, bridge

The Federal Executive Council, on Wednesday, approved N87.54 billion for the construction of some roads in parts of the country.

The amount approved included the cost variation for two existing road contracts.

Minister of the Federal Capital Territory, Muhammed Bello; and the Minister of Works and Housing, Babatunde Fashola, disclosed these to State House correspondents at the end of a meeting of the council presided over by President Muhammadu Buhari.

Bello told reporters that the contract for the road in the FCT was awarded to Messrs Gilmor Engineering Nigeria Limited in the sum of N30.69bn with a completion period of 32 months.

He said the contract was about the full scope development of Umaru Musa Yar’Adua Way to the Northern Express Way (Murtala Mohammed Way) popularly known as Kubwa Expressway.

He said the project area was within Phase II of the Federal Capital City, serving as boundary road between the adjoining districts of Mabushi, Kado, Katampe and Jabi.

READ ALSO: https://www.thexpressng.com/2020/11/05/fg-signs-n105b-afam-power-sale-agreement-thursday/

Fashola, on his part, said the council approved a variation of N47.5 billion for the completion of the 52 kilometre-Oyo-Ogbomosho Highway, which is a part of the Ilorin-Ibadan 145 kilometres highway.

The variation, he explained, had increased the cost of the contract to N105.04 billion.

He said the variation was necessary because of the need to adjust the thickness of the pavement from 500mm to 560mm; to change the asphalt to polymer-modified bitumen and also change the shoulders from surface dressing to fully asphalted inside and outside shoulder.

The minister explained, “So, all these required changes in prices of N47.5 billion. This was the revision that we presented which council approved.

“This road was awarded in 2010. As I said, Sections 1 and 3 were completed. We are trying to complete Section 2 which we also inherited.”

READ ALSO: https://www.thexpressng.com/2020/11/05/biden-launches-transition-website/

Fashola added that the council approved N9.35 billion variation to complete Lokko-Oweto Bridge that links Nasarawa to Benue State, adding that the development had changed contract price from N51.621bn to N60.961 billion.

He said, “That project was awarded in 2011 and it was awarded in three different sections – one section, the road to Benue to Oweto, was awarded to one contractor; we have completed that road.

“The bridge was awarded to another contractor. The bridge is essentially finished now. It is open to traffic. And then, Lokko to Nasarawa, 74 kilometres, was awarded to another contractor. We are trying to sort out that problem and we will come back to it.

“So, the approval given today was a N9.35 billion variation to complete the bridge component or remaining work on the bridge.”

He said changes in the contract moved the price from N51.62 billion to N60.96 billion.

Comments
Loading...